The duct before the beer flows: KS Abwassertechnik makes Esperantoplatz safe for Oktoberfest with BRAWOLINER®

KS Abwassertechnik rehabilitated leaking pipes underneath Esperantoplatz directly on the Theresienwiese in Munich in order to safeguard the festivities at the annual Oktoberfest.
The company relied completely on the quality products from
BRAWO
® SYSTEMS.

Technical details

  • Pipe size: DN 100 – 200 mm
  • Length of the rehabilitated section: approx. 375 metres
  • Number of pipes: approx. 10
  • Reason for rehabilitation: The affected pipes had several leaks, which could have posed a complication for the annual festival at the Munich Oktoberfest
  • Rehabilitation method: BRAWOLINER® HT with BRAWO® I & III resin and hot water curing
  • Rehabilitation time: approx. 2-3 weeks

Difficulty:

Tight time frame for the measures

Advantages and results

Above all, the trenchless rehabilitation method saved time and reduced risks, as no demolition work was necessary.

Conclusion

The pipe rehabilitation on Esperantoplatz was completed quickly and smoothly and guarantees a successful Oktoberfest, at least as far as the quality of the sewage network is concerned! As in previous projects, KS Abwassertechnik worked with the holistic solution provided by BRAWO® SYSTEMS.

Your press contact

Gunter Kaltenhäuser
BRAWO SYSTEMS GmbH
Blechhammerweg 13-17
67659 Kaiserslautern Germany
Tel.: +49 631 20561 - 260
Email: Gunter.Kaltenhaeuser@brawosystems.com
www.brawosystems.com